STATUT ACTUEL

Works in the DRC have achieved significant progress, marked by key milestones that reflect steady advancement. With the contract signed and contractors mobilised, the site is now fully established and operational, with the Employer’s Representative actively engaged on-site.
Construction continues to advance with work on a 10 kilometer road stretch, 5 meters of a total planned 15 meter embankment on the Luapula River, the installation of a crushing plant, and the establishment of the contractor’s accommodation and office sites.

RECENT HIGHLIGHTS

CARTES DU PROJET